About
Bookstore
Careers
Contact us
Events
Experts
Home
Links
Magazine
Membership
Specialty
Certification Benefits
Members Only
New Technology
Online
Publications
Sitemap
Privacy Policy |
Catskill/Delaware UV Disinfection Facility EIS
Mount
Pleasant, New York
HONOR AWARD— PLANNING
ENTRANT: Hazen and
Sawyer, P.C./CDM
ENGINEER IN CHARGE: Richard
Peters, P.E.
Project Description
Under a USEPA Filtration Avoidance Determination (FAD), NYCDEP must
build an ultraviolet light (UV) disinfection facility for the
Catskill/Delaware water supply, which provides 90% of the water used by
its 9 million customers. By building this facility, NYCDEP will avoid
the much costlier and disruptive construction of a filtration plant,
while providing increased health protection from water-borne
pathogens―specifically, Cryptosporidium.
A major step in
implementing this project is the preparation of a complex,
comprehensive environmental impact statement (EIS), encompassing
multiple alternatives and combinations of projects at the selected
site, and utilizing innovative techniques for identifying, preventing,
and mitigating potential environmental impacts.
Integrated Approach
The EIS entailed detailed evaluations of all potential environmental
impacts, including traffic, air quality, noise, and natural resources
impacts. Its aim is to minimize or avoid such impacts to the maximum
extent practicable by implementing feasible mitigative measures. These
impacts were also evaluated for ancillary facilities and unrelated
existing and planned facilities onsite. Examples include:
- Any traffic
impacts from hauling excavated material for filling/landscaping of the
Catskill/Delaware aerators will be mitigated through various measures
and, while some trees may be removed during final landscaping, six
acres surrounding the aerators will be restored using indigenous meadow
grass.
- Mitigation
measures for the three acres of wetland habitat to be impacted by
construction include restoration of temporary disturbances, enhancement
of disturbed/degraded wetlands, and wetland creation. Again, any
tree loss will be mitigated and is also addressed in the EIS’ overall
natural resources mitigation program.
Innovation
- Unprecedented
Scale: UV is an emerging technology for disinfecting drinking water.
The largest UV facility currently in service treats 180 million gallons
per day (mgd), while the Catskill/Delaware facility will treat 2
billion gallons per day (bgd) and will be, by far, the world’s largest.
The practical application of UV on this scale opens the door for other
large utilities to consider UV for their drinking-water facilities.
- Challenging EIS:
EIS preparation entailed overcoming a combination of challenges (e.g.,
large urban client, FAD timeframe, need to accommodate other facilities
onsite). The result is a thorough study/evaluation of the environmental
considerations associated with constructing such a large facility in a
highly developed area, with minimal impacts.
- Technological
Advancement: This project represents a tremendous leap forward for
drinking-water UV disinfection. Development of the largest UV units to
date, each capable of treating up to 40 mgd under worst-case
water-quality conditions and possibly 50 mgd under normal conditions,
contributes toward economical use of UV technology for cities and large
water purveyors, worldwide.
- EIS Roadmap: The
EIS should serve as a model to urban clients facing similar challenges
in siting and gaining acceptance for large-scale facilities. For
instance, the EIS calls for advanced stormwater management techniques
based on groundwater modeling. This model evaluated impacts of lowering
the water table during (and after) construction on the site’s wetlands,
leading to recommendations for enhancement of onsite wetlands instead
of engineered stormwater detention basins―an approach the host
community prefers. Another example was the use of low-sulfur fuels for
construction equipment. Impacts of using these fuels were quantified
and addressed within the EIS.
Social/Economic
Advancement
- Protecting Public
Health: UV provides enhanced disinfection of pathogens, including
Cryptosporidium. Ultimately, this project will benefit all residents
and visitors to New York via cleaner drinking water.
- Minimizing
Consumer Costs: The UV facility’s construction cost is estimated to be
about 1/4th that of a filtration plant. Its implementation is expected
to increase consumer water costs by only a few dollars per year―an
amazing bargain for a city that already offers one of the nation’s
lowest water rates.
- Reducing
Environmental Impacts: Building a filtration plant would have had
larger-scale environmental impacts over a longer construction period
than UV. Environmental impacts will be further reduced by the EIS’
innovative mitigation measures. For instance, construction impacts
(such as noise and traffic) will be mitigated or minimized. The EIS
also includes measures to protect the site’s extensive natural
resources (replanting of trees, stormwater BMPs, and wetland
enhancement/creation). And the facility’s footprint has been minimized
by using a fewer number of the largest practicable UV units, further
mitigating environmental impacts.
Complexity
One EIS, Many Components: Not only does the EIS support a
groundbreaking project, it integrates a multitude of additional items
into the UV project, taking into account other potential projects and
combinations of projects at the site and their individual and
cumulative impacts.
First, the EIS was
not limited to one facility at a given site. It incorporates many
components, with new components added as the design and EIS
progressed―all without impacting the USEPA-mandated EIS completion
schedule. Major additions included pressurization of two miles of
Catskill Aqueduct, which, along with the Delaware Aqueduct, feeds the
UV facility; provisions for maintaining water supply to users on the
Catskill Aqueduct during pressurization; a new 1-bgd screen chamber for
the Catskill Aqueduct; and improvements to facilities at the upstream
Kensico Reservoir, including filling decommissioned aerator basins and
landscaping the area in a manner acceptable to the host community.
These items significantly added to the complexity of the EIS, since the
engineering associated with each additional item was at a different
level of development than that of the overall UV facility. Engineering
studies and design efforts for various components were expedited, to
ensure that the impacts associated with each item would be
comprehensively represented within the EIS without impacting the
schedule.
The EIS also addressed other, unrelated onsite projects. Most notably,
NYC’s 290-mgd Croton Water Treatment Plant (WTP) was being considered
for construction at three alternative sites, one of which was the same
site as the UV facility―possibly during the same time period. Since
constructing both facilities would involve a greater scale of
construction than the UV project alone, consideration of impacts
associated with Croton WTP further escalated the EIS’ complexity. Other
potential facilities included in the EIS and planned at the same site
are a NYCDEP Police Precinct, shafts associated with the future
Kensico-City Tunnel, and possible relocation of the historic Hammond
House, currently located onsite.
|